title: "California Is Rebuilding Anderson Dam, and the Cost Estimates Do Not Agree"
description: "Santa Clara County's largest reservoir has been held near empty since 2020 on a federal safety order. Valley Water has now awarded a $1.88 billion construction contract. Published figures for what the whole project costs range from under $2 billion to $3.2 billion."
category: "California"
category_url: https://herald.la/category/california
author: "Valeria Ortiz"
published: 2026-07-31T04:55:40.000Z
updated: 2026-07-31T04:55:40.000Z
canonical: https://herald.la/article/california-is-rebuilding-anderson-dam-and-the-cost-estimates-do-not-agree
tags: ["infrastructure", "water", "seismic-safety", "santa-clara-county", "dams"]
---
# California Is Rebuilding Anderson Dam, and the Cost Estimates Do Not Agree

Santa Clara County's largest reservoir has been held near empty since 2020 on a federal safety order. Valley Water has now awarded a $1.88 billion construction contract. Published figures for what the whole project costs range from under $2 billion to $3.2 billion.

Anderson Reservoir, near Morgan Hill, holds about 90,000 acre-feet when it is
full. It has not been anywhere close to full since 2020, and it will not be again
until the middle of the next decade.

On July 24, Valley Water's board awarded a
[$1.88 billion construction contract](https://www.waterpowermagazine.com/news/valley-water-awards-us1-88bn-anderson-dam-contract/)
to the Flatiron Dragados Sukut joint venture to rebuild most of the dam. Work is
scheduled to start in early 2027 and to take about seven years.

## Why the reservoir was emptied

A stability evaluation in 2011 found that the dam's embankments
[could become unstable in a very large earthquake](https://www.valleywater.org/project-updates/c1-anderson-dam-seismic-retrofit),
and that a fault rupture beneath the structure could damage the outlet pipes and
intake works, the very equipment you would need to control a release. The dam was
built in 1950, to standards that predate most of what is now known about how
earth-fill dams behave in a strong shake.

In February 2020 the Federal Energy Regulatory Commission directed Valley Water to
draw the reservoir down to elevation 488 feet, effective October 1 of that year.
It has been held at roughly three percent of capacity since.

That is the part worth sitting with: the regulator's judgment was that the safest
version of this dam is one holding almost no water, for a decade and a half, in a
county that needs the storage.

## What the rebuild involves

This is not a patch. The plan replaces most of the dam and the spillway, installs
new high- and low-level outlets, and treats the foundation and seepage controls.
The reservoir stays essentially empty throughout construction, with the target for
full operation in 2034.

## The cost figures do not line up, and that is worth saying plainly

The construction contract is $1.88 billion. Beyond that, published totals diverge:
Engineering News-Record's coverage
[frames the rebuild as a $2.8 billion project](https://www.enr.com/articles/63390-californias-28b-anderson-dam-seismic-rebuild-moves-into-construction),
other trade coverage has described a $3.2 billion program, and Valley Water's own
project page lists a total cost of $1.77 billion without inflation and $1.97
billion with it.

Some of that gap is definitional: whether a figure covers only the dam retrofit or
the wider program of related work, and whether it is stated in current dollars or
escalated over a seven-year build. But the range is wide enough that anyone citing
a single number for this project should say which one they mean. On a public works
job of this size, funded by ratepayers, the definition is not a footnote.

## What it costs the county in the meantime

Santa Clara County has spent the drawdown years leaning harder on imported water.
[Roughly half the water used locally comes from outside the county](https://sanjosespotlight.com/dam-project-leaves-santa-clara-countys-largest-drinking-water-source-dry/),
and with its largest reservoir offline that dependence continues through
construction. Restoring the reservoir is expected to improve supply reliability,
support groundwater recharge and restore flood-control capacity on Coyote Creek.

## Why Southern California should pay attention

The Bay Area is not the only region with mid-century dams sitting near faults.
Aging water infrastructure across California is moving through the same cycle of
reevaluation, restriction and expensive reconstruction, including work on major
facilities in Los Angeles County.

Anderson is the case study for what that cycle costs when the answer comes back
"rebuild it": fourteen years between the finding and the finished dam, a decade of
lost storage in the interim, and a price tag that different official and trade
sources still describe differently.

## Sources

- [C1: Anderson Dam Seismic Retrofit](https://www.valleywater.org/project-updates/c1-anderson-dam-seismic-retrofit)
- [Valley Water awards US$1.88bn Anderson Dam contract](https://www.waterpowermagazine.com/news/valley-water-awards-us1-88bn-anderson-dam-contract/)
- [California's $2.8B Anderson Dam Seismic Rebuild Moves Into Construction](https://www.enr.com/articles/63390-californias-28b-anderson-dam-seismic-rebuild-moves-into-construction)
- [Dam project leaves Santa Clara County's largest drinking water source dry](https://sanjosespotlight.com/dam-project-leaves-santa-clara-countys-largest-drinking-water-source-dry/)